MANCHESTER AIRPORT

In Partnership With McLaren Construction

This project comprises of the construction of external yard service area circa 7,000m2 to the freight handling and logistics warehouse.

^

7,000m2 External Concrete yard brush finished slabs.

^

1,240m3 PAV2 Concrete.

^

200m.l. Expansion Joints.

^

796m.l Formed Restrained Movement Joints.

^

465m.l Saw Cut Joints.

^

418m.l Sawn Free Movement joints.

^

396m.l Isolation Joints.

^

600no. sheets A393 Mesh.

^

Brush finish to flatness tolerance (TR66)